Decision Framework for HVAC Installation Work Package Readiness and Lean Production Control: A Worked Example

Authors

  • Yasser Aboelmagd Vice Dean, College of Engineering, University of Business & Technology (UBT), Jeddah, Saudi Arabia; Mathematics and Physics Engineering Department, Faculty of Engineering, Alexandria University, Egypt.
  • Remon Eskander Engineering Programs Director, Field of Engineering, Alamein International University (AIU), New Al-Alamein City, Matrouh-Egypt; Structural Engineering Department, Faculty of Engineering, Alexandria University, Egypt.
  • Omnia Darwish Construction engineering Department, Higher institute of engineering and technology – ElBheira, Egypt

DOI:

https://doi.org/10.5281/zenodo.22976334

Keywords:

HVAC Installation, Work-Package Readiness, Lean Production Control, Last Planner System, Mechanical Construction, Decision Framework

Abstract

HVAC installation depends on the coordinated availability of approved designs, dimensionally compatible components, fabricated materials, site access, predecessor work, crew capacity, and inspection criteria. A scheduled installation task may therefore be impossible to execute even when it appears in the weekly plan. This conceptual study proposes a decision framework for assessing mechanical work-package readiness before release to installation crews. Eight evidence-based gate domains are combined into a binary release rule, while unresolved constraints are assigned owners and tracked through a look-ahead register. The framework distinguishes package readiness from weekly commitment reliability and measures accepted output, direct labor productivity, waiting, rework, and first-pass inspection yield separately. A hypothetical HVAC-zone example demonstrates the release decision and calculation of these measures, including how changes to the commitment denominator can distort reported performance. The example illustrates the framework’s logic; it does not establish productivity gains or waste reduction in an observed project. Prospective testing with package-level records, verified geometric tolerances, labor hours, and inspection outcomes is required to evaluate its effectiveness in mechanical installation practice.

References

Agbulos, A., Mohamed, Y., Al-Hussein, M., AbouRizk, S., & Roesch, J. (2006). Application of lean concepts and simulation analysis to improve efficiency of drainage operations maintenance crews. Journal of Construction Engineering and Management, 132(3), 291-299. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:3(291)

Al-Sudairi, A. A., Diekmann, J. E., Songer, A. D., & Brown, H. M. (1999). Simulation of construction processes: Traditional practices versus lean principles. In Seventh Conference of the International Group for Lean Construction (Vol. 7, pp. 39). https://iglc.net/papers/Details/59

ALARCÓN, L. F. (1997). Tools for the identification and reduction of waste in construction projects. Lean construction. https://tinyurl.com/y649efn4

AlSehaimi, A., & Koskela, L. (2008). What can be learned from studies on delay in construction? In 16th Annual Conference of the International Group for Lean Construction (pp. 95-106). The International Group for Lean Construction. http://iglc.net/Papers/Details/542

Aziz, R. F., & Hafez, S. M. (2013). Applying lean thinking in construction and performance improvement. Alexandria engineering journal, 52(4), 679-695. https://doi.org/10.1016/j.aej.2013.04.008

Ballard, G. (2000). Lean project delivery system. Lean Construction Institute. https://www.academia.edu/811452/Lean_project_delivery_system

Ballard, G., Kim, Y. W., Jang, J.-W., & Liu, M. (2007). Road map for lean implementation at the project level. The Construction Industry Institute, 426. https://tinyurl.com/33ffdskm

Ballard, G., & Tommelein, I. (2021). 2020 CURRENT PROCESS BENCHMARK FOR THE LAST PLANNER® SYSTEM OF PROJECT PLANNING AND CONTROL. https://escholarship.org/uc/item/5t90q8q9

Bashford, H. H., Walsh, K. D., & Sawhney, A. (2005). Production system loading–cycle time relationship in residential construction. Journal of Construction Engineering and Management, 131(1), 15-22. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:1(15)

Bertelsen, S., & Koskela, L. (2002). Managing the Three Aspects of Production in Construction. In 10th Annual Conference of the International Group for Lean Construction - Gramado, Brazil. https://iglc.net/papers/Details/175

Bølviken, T., & Koskela, L. (2016). Why hasn’t waste reduction conquered construction? In 24th Annual Conference of the International Group for Lean Construction (pp. 3-12). https://eprints.hud.ac.uk/id/eprint/29121

Construction Industry Institute (CII). (2005). Lean Principles in Construction (Research Summary 191-1). The University of Texas at Austin. https://www.construction-institute.org/lean-principles-in-construction

Construction Industry Institute (CII). (2007). Lean Implementation at the Project Level (Research Summary 234-1). The University of Texas at Austin. https://www.construction-institute.org/lean-implementation-at-the-project-level

Conte, A. S. I., & Gransberg, D. (2001). Lean construction: From theory to practice. AACE International Transactions, 10(1). https://www.researchgate.net/publication/283968828_Lean_construction_From_theory_to_practice

Deshpande, A. S., Filson, L. E., Salem, O. M., & Miller, R. A. (2012). Lean techniques in the management of the design of an industrial project. Journal of management in engineering, 28(2), 221-223. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000065

Feldmann, F. G. (2022). Towards lean automation in construction—Exploring barriers to implementing automation in prefabrication. Sustainability, 14(19), 12944. https://doi.org/10.3390/su141912944

Fernandez-Solis, J. L., Porwal, V., Lavy, S., Shafaat, A., Rybkowski, Z. K., Son, K., & Lagoo, N. (2013). Survey of motivations, benefits, and implementation challenges of last planner system users. Journal of Construction Engineering and Management, 139(4), 354-360. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000606

Formoso, C. T., Isatto, E. L., & Hirota, E. H. (1999). Method for waste control in the building industry. In Proceedings IGLC (Vol. 7, pp. 325). http://faculty.ce.berkeley.edu/tommelein/IGLC-7/PDF/Formoso&Isatto&Hirota.pdf

Formoso, C. T., Soibelman, L., De Cesare, C., & Isatto, E. L. (2002). Material waste in building industry: main causes and prevention. Journal of Construction Engineering and Management, 128(4), 316-325. https://doi.org/10.1061/(ASCE)0733-9364(2002)128:4(316)

Gabriel, E. (1997). The lean approach to project management. International Journal of project management, 15(4), 205-209. https://doi.org/10.1016/S0263-7863(96)00066-X

Green, S. D. (1999). The missing arguments of lean construction. Construction Management & Economics, 17(2), 133-137. https://doi.org/10.1080/014461999371637

Guo, H. (2009). Rethinking construction project management using the VP-based manufacturing management model. https://theses.lib.polyu.edu.hk/handle/200/4960

Howell, G., & Ballard, G. (1998). Implementing Lean Construction: Understanding and Action. https://me-l.co/2zohp7mh

Junior, A., Scola, A., & Conte, A. (1998). Last planner as a site operations tool. In the Proceedings of the 6th Annual Conference of the International Group for Lean Construction, Guarujá, Brasil. https://iglc.net/papers/Details/49

Kalsaas, B. T. (2013). Measuring waste and workflow in construction. In 21th Annual Conference of the IGLC. Fortaleza, Brazil (pp. 31-32). https://iglc.net/papers/Details/916?utm.com

Karim, M. R., Rodgers, D. C., & Hossain, M. A. (2024). The role of Internet of Things (IoT) in real-time supply chain monitoring. International Journal of Research and Innovation in Social Science, 8(10), 1800-1816. https://doi.org/10.47772/IJRISS.2024.8100157

Kim, Y.-W., & Ballard, G. (2010). Management thinking in the earned value method system and the last planner system. Journal of management in engineering, 26(4), 223-228. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000026

Koskela, L. (1992). Application of the new production philosophy to construction (Vol. 72). Stanford university Stanford, CA, USA. https://www.scirp.org/reference/referencespapers?referenceid=4150123

Koskela, L. (1997). Lean production in construction. Lean construction, 1-9. https://me-l.co/qgvshpvp

Koskela, L., Ferrantelli, A., Niiranen, J., Pikas, E., & Dave, B. (2019). Epistemological explanation of lean construction. Journal of construction engineering and management, 145(2), 04018131. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001597

Koskela, L., Huovila, P., & Leinonen, J. (2002). Design management in building construction: from theory to practice. Journal of construction research, 3(01), 1-16. https://doi.org/10.1142/S1609945102000035

Li, H., & Love, P. E. (1998). Visualization of building interior design to reduce rework. In Proceedings. 1998 IEEE Conference on Information Visualization. An International Conference on Computer Visualization and Graphics (Cat. No. 98TB100246) (pp. 187-191). IEEE. https://doi.org/10.1109/IV.1998.694218

Liu, G., Ma, Z., Li, J., Li, S., Zhou, X., & Song, Y. (2024). Framework of digital lean construction and implementation of its management platform for the construction phase. Journal of construction engineering and management, 150(6), 04024051. https://doi.org/10.1061/JCEMD4.COENG-14164

Love, P. E., Irani, Z., & Edwards, D. J. (2003). Learning to reduce rework in projects: Analysis of firm's organizational learning and quality practices. Project Management Journal, 34(3), 13-25. https://doi.org/10.1177/875697280303400303

Love, P. E., Mandal, P., Smith, J., & Li, H. (2000). Modelling the dynamics of design error induced rework in construction. Construction Management and Economics, 18(5), 567-574. https://doi.org/10.1080/014461900407374

Mao, X., & Zhang, X. (2008). Construction process reengineering by integrating lean principles and computer simulation techniques. Journal of Construction Engineering and Management, 134(5), 371-381. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:5(371)

Miller, C. J., Packham, G. A., & Thomas, B. C. (2002). Harmonization between main contractors and subcontractors: a prerequisite for lean construction? Journal of construction research, 3(01), 67-82. https://doi.org/10.1142/S1609945102000059

Mossman, A. (2005). Last Planner Overview: Collaborative Production Planning. Collaborative Programme Coordination, Lean Construction Institute, UK. https://l1nq.com/mdp2u7n

Mourmourakis, J., Shou, W., Wang, J., & Bai, Y. (2024). Analysing the alignment between lean construction and circular economy in prefabricated construction. In Annual Conference of the International Group for Lean Construction Iglc. https://doi.org/10.24928/2024/0128

Paez, O., Salem, S., Solomon, J., & Genaidy, A. (2005). Moving from lean manufacturing to lean construction: Toward a common sociotechnological framework. Human Factors and Ergonomics in Manufacturing & Service Industries, 15(2), 233-245. https://doi.org/10.1002/hfm.20023

Pedó, B., Formoso, C. T., Viana, D. D., Tzortzopoulos, P., Brandalise, F. M., & Whitelock-Wainwright, A. (2022). Visual management requirements to support design planning and control within digital contexts. Sustainability, 14(17), 10989. https://doi.org/10.3390/su141710989

Picchi, F. A., & Granja, A. D. (2004). Construction sites: using lean principles to seek broader implementations. In Proceedings of the 12th Annual Conference of the International Group for Lean Construction (IGLC-12), Helsingør, Denmark (pp. 3-6). https://iglc.net/Papers/Details/323

Pikas, E., Pedó, B., Tezel, A., Koskela, L., & Veersoo, M. (2022). Digital last planner system whiteboard for enabling remote collaborative design process planning and control. Sustainability, 14(19), 12030. https://doi.org/10.3390/su141912030

Sacks, R., Esquenazi, A., & Goldin, M. (2007). LEAPCON: Simulation of lean construction of high-rise apartment buildings. Journal of Construction Engineering and Management, 133(7), 529-539. https://doi.org/10.1061/(ASCE)0733-9364(2007)133:7(529)

Sacks, R., & Goldin, M. (2007). Lean management model for construction of high-rise apartment buildings. Journal of Construction Engineering and Management, 133(5), 374-384. https://doi.org/10.1061/(ASCE)0733-9364(2007)133:5(374)

Sacks, R., Koskela, L., Dave, B. A., & Owen, R. (2010). Interaction of lean and building information modeling in construction. Journal of construction engineering and management, 136(9), 968-980. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000203

Sacks, R., Radosavljevic, M., & Barak, R. (2010). Requirements for building information modeling based lean production management systems for construction. Automation in construction, 19(5), 641-655. https://doi.org/10.1016/j.autcon.2010.02.010

Salem, O., Solomon, J., Genaidy, A., & Luegring, M. (2005). Site implementation and assessment of lean construction techniques. Lean construction journal, 2(2), 1-21. https://pdfs.semanticscholar.org/f5c7/0520c749d700af800b450271f644393d378f.pdf

Salem, O., Solomon, J., Genaidy, A., & Minkarah, I. (2006). Lean construction: From theory to implementation. Journal of management in engineering, 22(4), 168-175. https://doi.org/10.1061/(ASCE)0742-597X(2006)22:4(168

Saradara, S. M., Khalfan, M. M. A., Jaya, S. V., Swarnakar, V., Rauf, A., & El Fadel, M. (2024). Advancing building construction: a novel conceptual framework integrating circularity with modified lean project delivery systems. Developments in the Built Environment, 20, 100531. https://doi.org/10.1016/j.dibe.2024.100531

Shewchuk, J. P., & Guo, C. (2012). Panel stacking, panel sequencing, and stack locating in residential construction: Lean approach. Journal of Construction Engineering and Management, 138(9), 1006-1016. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000520

Song, L., & Liang, D. (2011). Lean construction implementation and its implication on sustainability: a contractor’s case study. Canadian Journal of Civil Engineering, 38(3), 350-359. https://doi.org/10.1139/L11-005

Teicholz, P. (2004). Labor productivity declines in the construction industry: causes and remedies. AECbytes Viewpoint, 4(14), 2004. https://www.aecbytes.com/viewpoint/2004/issue_4.html

Tezel, A., Kifokeris, D., Koskela, L., Formoso, C. T., & Koch, C. (2022). A conceptual framework for lean construction and blockchain synergy. In Proceedings of the 30th Annual Conference of the International Group for Lean Construction (IGLC30) (pp. 576-587). https://doi.org/10.24928/2022/0162

Thomas, H. R., Horman, M. J., De Souza, U. E. L., & Zavřski, I. (2002). Reducing variability to improve performance as a lean construction principle. Journal of Construction Engineering and Management, 128(2), 144-154. https://doi.org/10.1061/(ASCE)0733-9364(2002)128:2(144)

Thomas, H. R., Horman, M. J., Minchin Jr, R. E., & Chen, D. (2003). Improving labor flow reliability for better productivity as lean construction principle. Journal of Construction Engineering and Management, 129(3), 251-261. https://doi.org/10.1061/(ASCE)0733-9364(2003)129:3(251)

Wambeke, B. W., Liu, M., & Hsiang, S. M. (2012). Using last planner and a risk assessment matrix to reduce variation in mechanical related construction tasks. Journal of Construction Engineering and Management, 138(4), 491-498. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000444

Womack, J. P., Jones, D. T., & Roos, D. (1990). The machine that changed the world (Vol. 1). Rawson Associates New York. http://220.247.223.182/files/DPS/The-machine-that-changed-the-world.pdf

Zegarra, O., & Alarcón, L. F. (2019). Coordination of teams, meetings, and managerial processes in construction projects: using a lean and complex adaptive mechanism. Production planning & control, 30(9), 736-763. https://doi.org/10.1080/09537287.2019.1578905

Zhang, Y., Tzortzopoulos, P., & Kagioglou, M. (2016). Evidence-based design in healthcare: A lean perspective with an emphasis on value generation. In Proceedings of the 24th Annual Conference of the International Group for Lean Construction, Boston, MA, USA (pp. 20-22). https://shorturl.fm/DJA1V

Ziaei, P. E., Malaeb, Z., Lusis, E., & Hamzeh, F. (2026a). Health-Check Framework for Assessing Last Planner System Implementation Using Social Network Analysis. 29-54. https://doi.org/10.60164/16jjgl0zs

Ziaei, P. E., Malaeb, Z., Lusis, E., & Hamzeh, F. (2026b). Health-Check Framework for Assessing Last Planner System Implementation Using Social Network Analysis. Lean construction journal, 29-54. https://doi.org/10.60164/16jjgl0zs

Published

2026-09-26

How to Cite

Decision Framework for HVAC Installation Work Package Readiness and Lean Production Control: A Worked Example. (2026). Reports in Mechanical Engineering, 7(2), 238-260. https://doi.org/10.5281/zenodo.22976334